KSEBOA - KSEB Officers' Association

Sunday
May 28th
Text size
  • Increase font size
  • Default font size
  • Decrease font size
Home News Power Sector News Kudankulam plant to start commercial operations in August

Kudankulam plant to start commercial operations in August

PDF
Hits smaller text tool iconmedium text tool iconlarger text tool icon
NPCILThe Nuclear Power Corporation of India Ltd (NPCIL), which is implementing the Kudankulam project, on 18-05-2012 said full commercial production of power at the 1,000MW first unit of the plant can start only in August. The NPCIL website, which had the deadline column blank since protests against the project began in October 2011, now says the first unit will be ready for commissioning in August 2012. Also, the deadline for the second unit, also of 1,000MW, is March 2013. There have been claims that power production will start soon, as early as June, and the second unit will be commissioned two months after the first unit goes fully commercial.

Two weeks back, chief minister J Jayalalithaa had said that the project would be ready in 10 days. Reacting to the CM's claim, plant officials had then said it would take at least 25 days more to start production.

Confirming the new deadline, project site director R Sundar said, "The deadline is for the first unit to start producing the entire 1,000MW. Since this is the first reactor of the plant, that too of a new type (VVER), we need to get clearance from the Atomic Energy Regulatory Board (AERB) at each and every stage. The entire production of 1,000MW is possible only in August."

The fuel loading will begin latest by first week of June but that may not lead to production of full 1,000MW immediately. Fuel will be loaded stage by stage and power production will increase gradually and the plant will attain full capacity of 1,000MW in August, he said. Though the state may start getting power from the plant once the generation begins, it may be a while before it gets its full share of 450MW from the first unit.

For a state which is juggling with its meagre power resources, this is bad news. The power demand in the state peaks during the hot summer months of April, May and June, and any additional power is crucial during the period.

After getting clearance from AERB, the plant officials on May 10 started removing the dummy fuel loaded into the reactor in 2010. The officials said loading of uranium fuel would commence after another round of inspection by AERB officials. As part of IAEA inspection, which is mandatory, a team from HRID Ltd, a Croatian company dealing with certification of nuclear reactors, will check the reactor pressure vessel and other systems of the first unit next week. Teams from AERB and NPCIL will also be present during the inspection," Sundar said.

The original deadline for the Russian-aided project, launched in 2001, was December 2007 for the first unit and December 2008 for the second unit. When the project got delayed due to various reasons, NPCIL set a new deadline of December 2011 for the first unit. However, with protests against the project beginning in October 2011 and officials and workers being prevented from entering the plant site, the commissioning date was put off to March 2012. But when there was sign of the protests ending, NPCIL removed the commissioning date from its website.

Source- Times of India

 

Add comment


Security code
Refresh

20-conference
 

Random Videos

You need Flash player 6+ and JavaScript enabled to view this video.
Title: Power Quiz 2015 Final - Part-1

Latest Comments

Banner

Reference Book

 

Reference Book on Power

Electrical Engineering-- D' 1/4 Size Hard bound-- 1424 Pages-- Just Rs.1000/- only &n...

Visitors Counter

mod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_countermod_vvisit_counter
mod_vvisit_counterToday4023
mod_vvisit_counterYesterday4600
mod_vvisit_counterThis Month132853
mod_vvisit_counterLast Month152890

Online Visitors: 95
IP: 54.162.44.105
,
Time: 17 : 43 : 38